บริษัท เจจีเจดี จำกัด

Our Archievements

TPIPP, 2024

Mukdahan municipality waste to energy power plant project, designed for production capacity of 9.9 MW with 2*350 t/d grate boilers, is now preparing for civil construction.

TPIPP, 2024

Grate boiler of MSW with a capacity of 750t/d waste incineration, including the auxiliary equipment, purchase, installation, debugging, operation, and maintenance of relative material and the relevant civil construction. The project started in the mid of 2023 and it be handed over in October 2024.

TPIPP, 2022

This project contains 2 parts: the first is to modify the existing coal fired boiler into a 110t/h RDF fired circulating fluidized bed boiler. The second is to build a new 130t/h RDF fired circulating fluidized bed boiler as an addition aside the existing boiler. The project completed and handed over in July 2023.

TPI, 2018

The company started construction work of 3*750T/D Grate Boiler Project of WTE Power Plant, and the project was put into production in July ,2020.

TPI, November 2016

The company started construction work of 2*750 T/D Grate Boiler for Waste to Energy Power Plant of TPI, and the project was completed in May, 2018.

TPI, 2016

The company started construction work of TPI company 35t/h CFB boiler/6MW Coal Fired Power Plant in year 2016, and the project was handed over to TPI and has been operated by TPI since September,2017.

TPI, February 2015

The company contracted EPC project 2*75 t/h Boiler of RDF Power Plant of Thai TPI Polene Power Public Co,Ltd.This project was completed in September ,2016, started operation in May,2017 and handed over to the Owner and was operated by the owner in December, 2015.

SCG, August 2014

The company contracted Thai SCG-4MW Biomass Power Plant Project of China Sinoma Energy Saving Co.,Ltd. This project was completed and handed over to the Owner in December, 2015 and has been in normal operation until now.

TPI, March 2013

The company contracted an EPC project of 35 t/h CFB boiler/6 MW coal fired power plant of TPI Thailand. This project mainly composes of one unit of 35 t/h CFB boiler and one unit of 6MW extraction condensing steam turbine generator unit. This project was handed over to TPI in May,2014 and has been in normal operation till now.